SIIP Project Phase 6/7 - Dashboard Snapshots

Phase 6 and Phase 7 mainly focused on the remainder of the I-95/I-395/I-495 interchange, mainly the elevated ramps, but also included the remainder of the northbound I-95 roadway south of I-495. Phases 6 and 7 were constructed in one contract, was advertised for bids by VDOT on June 24, 2003, the bids were opened on September 3, 2003, the Commonwealth Transportation Board awarded the $99.8 million contract on September 17, 2003, to Archer Western Contractors Ltd., and contract completion occurred on July 17, 2007.

The VDOT Dashboard has the details for this project, here is a copy from March 31, 2007 below, from the I95/I395/I495 Interchange (SIIP Phase 6/7) project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $105,895,000
Cost of Work To Date - $94,010,006
Current Contract Amount - $103,486,107
6.0% OVER ORIGINAL CONTRACT AWARD AMOUNT
Contractor's Notice to Proceed - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 91%
% Critical Work Planned - 93%
Days Charged To Date - 1261
Current Number of Days - 1370
TODAY <= PROJECTED COMPLETION DATE AND PROJECTED COMPLETION DATE <= ORIGINAL COMPLETION DATE

The VDOT Dashboard has the details for this project, here is a copy from December 4, 2006 below, from the I95/I395/I495 Interchange (SIIP Phase 6/7) project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $105,895,000
Cost of Work To Date - $85,214,972
Current Contract Amount - $103,209,089
6.0% OVER ORIGINAL CONTRACT AWARD AMOUNT
Contractor's Notice to Proceed - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 81.5%
% Critical Work Planned - 86.9%
Days Charged To Date - 1190
Current Number of Days - 1370
TODAY <= PROJECTED COMPLETION DATE AND PROJECTED COMPLETION DATE <= ORIGINAL COMPLETION DATE

The VDOT Dashboard has the details for this project, here is a copy from August 26, 2006 below, from the I95/I395/I495 Interchange (SIIP Phase 6/7) project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $106,500,000
Cost of Work To Date - $75,916,167
Current Contract Amount - $103,198,218
6.6% OVER ORIGINAL CONTRACT AWARD AMOUNT
Contractor's Notice to Proceed - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 73.3%
% Critical Work Planned - 82.0%
Days Charged To Date - 990
Current Number of Days - 1369
TODAY <= PROJECTED COMPLETION DATE AND PROJECTED COMPLETION DATE <= ORIGINAL COMPLETION DATE

The VDOT Dashboard has the details for this project, here is a copy from April 20, 2006 below, from the I95/I395/I495 Interchange (SIIP Phase 6/7) project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $108,000,000
Cost of Work To Date - $66,524,896
Current Contract Amount - $103,136,388
8.1% OVER ORIGINAL CONTRACT AWARD AMOUNT
Start Date - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 64.1%
% Critical Work Planned - 80.0%
Days Charged To Date - 899
Current Number of Days - 1369
15% BEHIND SCHEDULE

The VDOT Dashboard has the details for this project, here is a copy from January 21, 2006 below, from the I95/I395/I495 Interchange project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $99,829,000
Cost of Work To Date - $57,590,022
Current Contract Amount - $103,129,388
3.3% OVER ORIGINAL CONTRACT AWARD AMOUNT
Start Date - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 55.3%
% Critical Work Planned - 74.0%
Days Charged To Date - 809
Current Number of Days - 1369
18% BEHIND SCHEDULE

The VDOT Dashboard has the details for this project, here is a copy from October 30, 2005 below, from the I95/I395/I495 Interchange project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $99,829,000
Cost of Work To Date - $49,073,247 
Current Contract Amount - $103,118,909
3.2% OVER ORIGINAL CONTRACT AWARD AMOUNT
Start Date - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 47.0%
% Critical Work Planned - 65.0
Days Charged To Date - 717
Current Number of Days - 1369
18% BEHIND SCHEDULE

The VDOT Dashboard has the details for this project, here is a copy from July 26, 2005 below, from the I95/I395/I495 Interchange project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $103,026,894
Cost of Work To Date - $38,904,365
Current Contract Amount - $103,026,894
3.2% OVER ORIGINAL CONTRACT AWARD AMOUNT
Start Date - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 36.8%
% Critical Work Planned - 48%
Days Charged To Date - 625
Current Number of Days - 1369
11% BEHIND SCHEDULE

Copyright 2006 by Scott Kozel. All rights reserved. Reproduction, reuse, or distribution without permission is prohibited.

Back to top

By Scott M. Kozel, Roads to the Future

(Created 12-4-2006, updated 9-16-2007)